Progress Report on the Renovations
June 20, 2005



By the time that you read this, M.P. Lundy, Construction Managers for the renovation project, will have been working for seven weeks. Progress on the work has been very satisfactory, with the crypt area moving ahead on schedule.

Presently, all the major excavation of the crypt has been completed, which has allowed the installation of the wood beam reinforcement and the new steel columns. Concrete retaining wall work is substantially done and the concrete floor is expected to be completed during the second week of July.

In the existing basement area, central electrical equipment is being installed which will allow the installation of electrical distribution systems during July. New boilers have been ordered and are expected to be installed in mid August.

In The Well area, the under-floor drainage system serving the kitchen and the new washrooms and showers has been completed, allowing the start of partitions and drywall.

The firm of T. Harris Environmental Management Inc has been re-engaged to do a full investigation of the facilities to ensure that no mould is present in any of the areas exposed following the demolition work. This investigative work will be completed in early July.

It's encouraging to report that up to the present there have been no "surprises" and therefore the cost of the work is staying within budget estimates. We are working with M.P. Lundy to see if a firm price contract can be established for the balance of the work. This will go a long way to ensuring that all the work will completed within approved budgets.

 